Communication Technology

 

 

 

AST

AST SpaceMobile is a publicly traded satellite designer and manufacturer based in Midland, Texas, United States. The company is building the SpaceMobile satellite constellation, a space-based cellular broadband network that will allow existing, unmodified smartphones to connect to satellites in areas with coverage gaps. At the heart of AST SpaceMobile's value proposition is the fact that users will be able to connect to the company's satellites directly with their smartphones, without the need for specialized devices or satellite antennas. This is made possible by the satellites effectively acting as cell towers in space, using cellular spectrum and protocols, as opposed to traditional satellite spectrum and protocols. The earlier company description cited agreements and understandings with over 40 mobile network operators. Partner counts are dated business figures; they do not establish commercial availability in every partner market. The service will be available to the company's mobile network operator customers, which collectively represent a significant number of subscribers. The technology targets coverage gaps. Connectivity inside vehicles or buildings depends on penetration loss, visibility, antenna orientation and available link margin; indoor service is not a universal guarantee. The company's BlueWalker 3 prototype demonstrated a large deployable array in low Earth orbit. Later BlueBird spacecraft use larger arrays, so the prototype's former size record is historical. The satellite maintains low Earth orbit at an altitude between approximately 508 and 527 km (316 and 327 miles).

The photograph shows BlueWalker 3’s large tiled antenna array during ground work. The array places much of the antenna capability on the satellite, compensating for the small antenna and limited transmit power of an ordinary handset.

BlueWalker 3 phased-array hardware laid out indoors with the engineering team behind it

Orbit and Constellation

The early plan described 243 satellites. The April 2026 FCC order instead authorizes a 248-satellite configuration, subject to its conditions; an authorized total is not a count already in service. The company's satellites effectively act as cell towers in space, using cellular spectrum and protocols, as opposed to traditional satellite spectrum and protocols. The first five commercial BlueBird satellites, known as Block 1, launched on 12 September 2024. Indoor coverage remains dependent on propagation conditions and service availability, rather than being guaranteed by the constellation design

The historical illustration below labels AST at 725–740 km with 243 satellites. Those are earlier planning values. The April 2026 authorization lists several lower orbital configurations, including a 460 km case and nominal apogees near 520, 685 and 690 km. DA 26-391, pages 2–3.

An orbital plane is the geometric plane containing an orbit around Earth. Multiple satellites can follow approximately the same orbital path, separated along it. Different planes can have the same altitude but different orientations. Inclination describes the tilt relative to the equator; it is not a second altitude.

Historical orbit comparison showing an early AST plan at 725 to 740 km and 243 satellites

Authorized orbital groups

The following groups total 248 satellites in the April 2026 grant. The perigee and apogee are nominal values. The grant specifies altitude tolerances of plus or minus 30 km and inclination tolerances of two degrees.

Satellites

Perigee / apogee

Inclination

Additional scope

5

515 / 520 km

53 degrees

Existing first five; operations down to 425 km also specified

22

515 / 520 km

53 degrees

Deployment at 520–530 km

1

460 / 460 km

50 degrees

Separate modified orbital case

192

685 / 690 km

53 degrees

Deployment at 530 km; operations down to about 530 km

28

680 / 685 km

98.1318 degrees

Deployment at 530 km; operations down to about 530 km

  • Deployment altitude, permitted operating range and current tracked altitude are different quantities.

Spectrum and Bandwidth

The handset link and the gateway link use very different frequencies. The handset uses cellular spectrum under the relevant operator and regulatory arrangements. High-frequency feeder links connect the satellite to ground infrastructure.

  • AST SpaceMobile has achieved space-based LTE speeds of more than 10 Mbps using leased AT&T spectrum and Nokia Radio Access Network gear for testing.
  • The September 2023 announcement reported a 5G call and a separate download test of approximately 14 Mbps; these should not be treated as one measured 5G session.
  • The five Block 1 satellites launched in September 2024. The April 2026 FCC authorization covers a total configuration of 248 satellites, including further deployment.
  • The company's satellites effectively act as cell towers in space, using cellular spectrum and protocols, as opposed to traditional satellite spectrum and protocols.
  • Indoor and in-vehicle connectivity depends on the actual link budget and obstruction; a successful outdoor test does not guarantee service in every building.

U.S. direct-to-cell Spectrum / RF details

The order lists these U.S. Supplemental Coverage from Space ranges separately from overseas operations. The uplink is Earth-to-space, so its transmitter is the phone. The downlink is space-to-Earth, transmitted by the satellite.

Service group

Phone uplink

Satellite downlink

Scope

Lower 700 MHz

698–716 MHz

728–746 MHz

AT&T-related SCS spectrum and geographic conditions

FirstNet Band 14

788–798 MHz

758–768 MHz

FirstNet agreement and public-safety conditions

Cellular 800 MHz

824–849 MHz

869–894 MHz

AT&T / Verizon arrangements; airborne-device restriction applies

The listed ranges are authorization envelopes. The usable carrier and bandwidth depend on the underlying spectrum rights, geography and deployment. They do not imply that one phone transmits across the entire range. DA 26-391, page 4 and grant conditions 1–4.

Outside-U.S. service spectrum

The same FCC order lists a broader set of direct-to-cell frequencies for operations outside the United States. Those entries remain subject to national permissions, certification requirements and interference conditions; they are not worldwide landing rights.

Direction

Ranges in MHz

Earth-to-space

663–748; 777–798; 807–862; 880–915

Space-to-Earth

617–652; 728–821; 852–894; 902–960

Do not pair these broad envelopes into a single invented FDD band. They cover different regional arrangements. The order specifically explains that its listing alone does not approve direct-to-cell operation outside the U.S. in 902–928 MHz. DA 26-391, page 4, footnote 14 and condition 1.

Feeder links and TT&C

Gateway links carry traffic between space and the terrestrial network, while TT&C controls the spacecraft. Their frequencies must not be confused with handset bands. Emergency channels also have narrower purposes than normal broadband operation.

Function

Frequency / centres

Direction and restrictions

Feeder and nominal TT&C

37.5–42.0 GHz

Space-to-Earth

Feeder and nominal TT&C

45.5–47.0 GHz

Earth-to-space; outside U.S. only

Feeder and nominal TT&C

47.2–50.2 and 50.4–51.4 GHz

Earth-to-space

LEOP / emergency TT&C

2047, 2048, 2056, 2057, 2058, 2077 MHz; each 192 kHz

Earth-to-space, within 2025–2110 MHz; outside U.S. only

LEOP / emergency TT&C

2225, 2226, 2234, 2235, 2236, 2244 MHz; each 768 kHz

Space-to-Earth, within 2200–2290 MHz; outside U.S. only

Emergency TT&C

430.5, 432.3, 434.1, 435.9, 439.5 MHz; each 50 kHz

Both directions, outside U.S. only; 24-hour limit specified for the 243 satellites other than BlueBird 1–5

Onboard GPS reception

1575.42 and 1176.45 MHz

Receive-only positioning, navigation and timing; not a subscriber service

The feeder allocations contain gaps, especially 50.2–50.4 GHz. They are not one continuous 37.5–51.4 GHz band. Exact waveform bandwidths and centre-frequency options remain in the grant. DA 26-391, pages 5–6.

  • A smartphone communicates in the cellular band; it does not need a V-band feeder-link radio.

Roadmap and Constellation

The table below is retained as a historical 2025 presentation roadmap. Its block names, capacity ratios and broad tuning ranges are design descriptions. The later FCC grant provides a different, dated authorization baseline.

SATELLITE PROGRAM

BW3
Launched 9/2022

BlueBird Block 1 (BB1)
Launched 9/2024

BlueBird Block 2 (BB2)

BlueBird Block 3

NUMBER OF SATELLITES

1 (testing sat)

5

Up to 248 (2025 presentation roadmap; not an additional authorized total)

ORBIT

520 km

520 km

520 km/690 km

690 km

ARRAY SIZE

~693 sq ft

~693 sq ft

~2,400 sq ft

~2,400 sq ft

CAPACITY

X

10x BW3

100x BW3

100x BW3

BANDS

700 – 960 MHz FDD

700 – 960 MHz FDD

700 – 960 MHz FDD

1.4 – 2.4 GHz FDD

Source : 6G@UT Forum 2025: AST SpaceMobile System and Supplemental Coverage from Space for D2C

The FCC’s April 2026 configuration totals 248 spacecraft including the first five. Therefore, the roadmap’s shared Block 2 / Block 3 cell must not be added to the Block 1 count to derive a licensed fleet of 253. The roadmap also rounds orbital heights, while the FCC separately specifies perigee, apogee, tolerances and operational ranges.

The 700–960 MHz and 1.4–2.4 GHz rows describe broad roadmap ranges. They are not continuous operating allocations. In particular, the 2026 order reviewed here does not establish a Block 3 subscriber authorization across 1.4–2.4 GHz. This part of the presentation remains a development roadmap, not a verified deployed capability.

Capacity ratios need a defined reference and traffic model. A 100-times comparison does not mean that every handset becomes 100 times faster. Array size, processing bandwidth, spectrum reuse and simultaneous user loading affect different parts of network capacity.

  • Use the roadmap to understand design evolution, and the dated authorization to identify permitted operations.

Demonstrated Capability

Demonstrations establish that a connection worked under the reported test conditions. They do not establish continuous coverage, a guaranteed rate or commercial availability everywhere. The dates below preserve the difference between early tests and operational service.

Date

Event

Details

From 2024 (historical testing summary)

Ongoing Testing

  • Worldwide testing of broadband connections using BB1 satellites with partner MNOs

  • Testing capabilities for government applications

September 2023

5G call
Separate download test: approximately 14 Mbps

In a 5G first ever, demonstrated space-based 5G connectivity by placing a call from Maui, Hawaii, USA, to a Vodafone engineer in Madrid, Spain, using AT&T spectrum.

June 2023

LTE testing
Initial download speeds above 10 Mbps

In an LTE first ever, using AT&T cellular spectrum, connected everyday smartphones using BW3 satellite.

April 2023

2G Voice Call

The first voice call was made from Midland, Texas area to Rakuten in Japan over AT&T spectrum using a Samsung Galaxy S22 smartphone.

The September 2023 announcement identifies a 5G call on 8 September using a Samsung Galaxy S22 and AT&T spectrum. It reports approximately 14 Mbps in a separate download test. The public announcement does not justify labelling that throughput as the result of the same 5G call. AST September 2023 announcement.

For comparison, a peak-rate design target describes what a system is intended to support. A measured download rate describes one test. Commercial user throughput additionally depends on scheduling, spectrum, signal quality and other users sharing the beam. The historical table should therefore be read as evidence of milestones, not a service-level agreement.

  • Keep demonstrated throughput, per-cell design peaks and guaranteed user service separate.

Direct-to-Cell Architecture and Practical Constraints

The handset has a small antenna and limited transmit power. AST places a large phased array on the spacecraft to receive that weak signal. Ground infrastructure then connects the satellite path to the mobile operator.

Phone, satellite, gateway and mobile operator

The signal follows two different radio links before it reaches the operator network. The user link uses cellular spectrum. The feeder link serves a ground gateway, where the connection enters the terrestrial infrastructure.

AST’s architecture description assigns compensation for delay and Doppler to its gateway technology. Satellite motion changes propagation delay and frequency offset continuously. Supporting an ordinary handset therefore requires network-side handling of those effects. The public description is high level; it does not expose the complete PHY timing or scheduler implementation. AST: How it works.

Coverage, capacity and handset compatibility

A satellite footprint describes where a beam could reach under suitable geometry. Service also requires a compatible band, operator integration, authorization and sufficient signal margin. These conditions explain why a large footprint is not a continuous-service guarantee.

A building or vehicle adds penetration loss. Trees, terrain and body blockage can reduce the margin further. Increasing satellite array gain helps the link budget, but does not remove these losses. The network also shares resources among users within each coverage cell, so coverage area and per-user throughput are different measures.

Direct-to-cell describes the endpoint relationship. It does not by itself establish that a phone implements every Release 17 or later 3GPP NTN feature. AST targets existing cellular handsets; a specific protocol capability must be supported by device and network evidence. The 2026 order separately addresses device-certification waivers and partner spectrum arrangements.

  • Large satellite antennas support the weak handset link; gateway processing and operator integration remain essential.

BlueWalker and BlueBird Evolution

BlueWalker 3, BlueBird Block 1 and the larger next-generation BlueBirds represent different development stages. The progression combines flight demonstration, initial commercial spacecraft and increased antenna and processing capability. It should not be reduced to satellite count alone.

BlueWalker 3 and BlueBird Block 1

BlueWalker 3 provided an in-orbit test platform for direct connections with ordinary phones. The first five commercial BlueBirds followed in September 2024. A successful launch established deployment progress, while service continuity still depended on further constellation growth.

The Block 1 launch announcement described planned non-continuous service. That qualification matters: a small initial fleet cannot be assumed to give uninterrupted visibility everywhere. The 693-square-foot array class appears in both the retained roadmap and AST’s architecture description. AT&T, 12 September 2024.

Next-generation BlueBird and Block 3 roadmap

AST describes next-generation BlueBirds with arrays of approximately 2,400 square feet and an AST5000 processing platform. The company presents these as capability improvements, while the reviewed FCC order defines the licensed constellation and frequency scope.

The next-generation product page lists BlueBird 6 as launched in December 2025 and subsequent launches in 2026. It advertises 10 GHz of processing bandwidth and peak rates above 150 Mbps per coverage cell. These are company design-capability figures, not 10 GHz of licensed handset spectrum or a guaranteed rate for each user. AST next-generation BlueBird overview.

The historical Block 3 column is retained with its source. The reviewed sources do not establish a separately deployed Block 3 fleet or a complete Block 3 RF authorization. Where the FCC groups spacecraft by orbit, this note uses those groups rather than assigning every group to a marketing block without evidence.

  • Processing bandwidth, licensed RF bandwidth and delivered throughput describe different quantities.

Spectrum and Altitude Comparisons

The comparison separates hardware evolution from regulatory frequency rights. The historical roadmap describes spacecraft blocks; the April 2026 grant specifies bands and orbital groups. A spacecraft block does not automatically acquire every frequency in its tuning range.

Stage

Array / role

RF interpretation

BlueWalker 3

Prototype; about 693 square feet in historical roadmap

Experimental test permissions must be identified separately

BlueBird Block 1

Five commercial spacecraft; 693-square-foot class

Included in the constellation grant; cellular user links separate from feeder links

Next-generation BlueBird

Approximately 2,400-square-foot arrays

Use applicable grant and operating conditions, not the whole broad tuning envelope

Block 3 roadmap

Historical presentation column

No independently verified deployed fleet or complete new RF plan established here

Color-coded spectrum bands

The handset plot uses separate colors for the three U.S. SCS groups. The feeder plot uses separate colors for link direction and the outside-U.S. band. This avoids presenting the same authorization as three different generation-specific grants.

U.S. SCS subscriber frequencies: April 2026 grantU.S. SCS subscriber frequencies: April 2026 grant680700750800850900Lower 700: phone UL698 - 716Lower 700: satellite DL728 - 746FirstNet: phone UL788 - 798FirstNet: satellite DL758 - 768Cellular: phone UL824 - 849Cellular: satellite DL869 - 894MHz

Figure 1. Colors identify service groups, not satellite generations. All ranges remain subject to the grant and applicable spectrum arrangements. Source: DA 26-391, page 4.

Feeder links and nominal TT&C: April 2026 grantFeeder links and nominal TT&C: April 2026 grant374043464952Satellite to gateway37.5 - 42.0Gateway to satellite47.2 - 50.250.4 - 51.4UL outside U.S. only45.5 - 47.0GHz

Figure 2. The 50.2–50.4 GHz gap is preserved. The purple band is restricted to outside-U.S. operations. These are gateway frequencies, not phone frequencies.

Each endpoint is a band boundary. The charts do not depict the bandwidth of a particular transmission. TT&C and outside-U.S. subscriber bands remain in the detailed tables because their purpose and conditions differ.

Orbital altitude by authorized group

The altitude plot shows nominal perigee-to-apogee intervals from the grant. It groups the five and twenty-two spacecraft entries where their nominal intervals coincide. It does not show a live satellite tracking inventory.

Authorized groups: nominal perigee-to-apogee intervalsAuthorized groups: nominal perigee-to-apogee intervals4505005506006507001 satellite / 50 deg460 / 460 km5 + 22 / 53 deg515 / 520 km192 / 53 deg685 / 690 km28 / 98.1318 deg680 / 685 kmkm

Figure 3. Nominal perigee / apogee from DA 26-391, pages 2–3. Counts total 248 authorized satellites. Altitude tolerances, lower operating permissions and deployment altitudes are excluded from these bars; see the orbit table.

A line at 460 km represents the circular nominal case. Short bars near 520 and 690 km represent slightly different perigee and apogee values, not multiple generation heights. The plus or minus 30 km tolerances and permitted lower operating altitudes are documented in the orbit table rather than included in these nominal bars.

  • Read each plot with its date and scope; nominal authorization values are not current measured positions.

FCC

The 2026 FCC order changes the regulatory baseline from early deployment permissions to a larger constellation with SCS authority. The earlier public notice records the request stage; the later order records a conditional grant.

[1] AST&Science; LLC  

Key records and authorization scope

These two records are useful together because they distinguish a filed request from the resulting authorization. The 2026 order includes its own orbit and frequency schedule as well as conditions on geography, devices and interference.

Record

Status

Coverage in this update

DA 25-815

5 September 2025 public notice

Application and spectrum descriptions on pages 1–4; acceptance for filing was not approval.

DA 26-391

21 April 2026 Authorization and Order, S3065

Grant schedule on pages 2–6 and initial conditions on pages 6–7; total 248 satellites.

The 2026 grant authorizes 223 additional satellites beyond the 25 previously authorized. This is a licensing progression, not a statement that 248 satellites were already launched. The order also separates U.S. SCS from direct-to-cell operations outside the U.S., which remain subject to additional national and certification requirements.

Interference and operating conditions

The grant permits service subject to conditions that matter to the technical design. Beam coverage must respect spectrum rights and geographic boundaries, while interference protection remains necessary even when the phone itself requires no special satellite antenna.

For the specified CONUS waiver, aggregate field strength outside leased areas must not exceed 40 dBµV/m unless the affected licensee agrees otherwise. The order requires notification near neighboring co-channel license boundaries and resolution of interference. It also prohibits the specified 800 MHz service to airborne devices. These are examples from the grant, not an exhaustive operating checklist.

The source review covered the frequency and orbit schedule and the initial grant conditions, together with selected operator announcements. The remaining conditions and legal analysis were not reviewed exhaustively. A specific service deployment must use the complete applicable authorization rather than this explanatory summary.

  • FCC authority, actual deployment and commercial availability are separate milestones.